Project Summary:- Supply, Design, Engineering, Testing, commissioning of Burners, combustion fan, related burner valves and equipment's, PT and DPT transmitters and Allen Bradley Logix platform PLC & Training of System.
Objective:-
Project Summary:- Supply, Design, Engineering, Testing, Commissioning of New Rockwell CLX PLC System, Required Modification in the Local SCADA and Integrating with Emerson Make Wireless Gateways.
Objective:-
Project Summary:- Supply, Design, Engineering, Testing, Commissioning of New Rod Feeder Machines in HDC-1 & HDC-2 Casting Station Ch-02 with New Dedicated Rockwell CLX PLC System along with Power Flex 750 Series VFD's. Including all related field cablings works, Trunking, Testing and Commissioning
Objective:-
Project Summary:- Supply, Design, Engineering, Testing, Commissioning of New Marking Machine and Integration with New Rockwell Logix L3x and PanelView Plus 7 HMI for Graphic Display & Alarams. Laying of New Power Cables, CAT6 Cables and Pneumatic Air Pipe Tapping.
Objective:-
Project Summary:- Design, Supply, Engineering, Testing, Commissioning & Training of New dedicated Control Logix PLC Control System, Provision of SCADA Connectivity, ATS Panel for the New Supplier Dryer Package Unit In Cast House 1 & 2.
Objective:-
Project Summary:- Design, Supply, Engineering, Testing, Commissioning & Training of Field instrumentation (Magnetic flowmeter, Vortex flowmeter for Blended and unblended line, Ultrasonic Level TX for Hotwell & Coldwell, Position switch for manual valve and DP switch to Duplex filters) and integrated to existing ControlLogix PLC system.
Objective:-
Project Summary:- Design, Supply, Test and Commissioning of Control System Make SIEMENS SIPLUS S7-1500 ET200 Series PLC system, Rockwell SMC50 Soft starters enclosed on Form 4 Type 6 Elsteel Make MCC Panel to New Hydraulic Pack for Penstocks and HOV Valves and Cylinder system.
Objective:-
Stormwater and groundwater enter the TPS overflow chamber from a DN10 m tunnel. The Stormwater flow deliver to the Arabian Gulf via duckbill diffusers through Terminal pump station. The Penstock and HOV vales are work on Hydraulic system which inflatable dam and stop logs will be used to prevent backflow of tidal seawater into the overflow channel during maintenance activities.
Pumped flows and flows in the overflow channel are measured and recorded in ICA/SCADA to provide total TPS discharge flows.
Project Summary:- Supply, Design, Engineering, Testing,
Commissioning of New LED Display Board
(SIEBERT) and Integration with existing
Rockwell Logix PLC in Cast house Complex.
Objective:-
Project Summary:- Supply, Design,
Engineering, Testing, commissioning of Control System
with Rockwell CLX PLC and PF 753 VFD for
the New Vibro Feeder Machine.
Objective:-